With the laying of the first asphalt layer in the construction section between Hauptstraße and the Falltorstraße/Mozartstraße junction, you can already start to get an idea of what Schillerstraße will look like in a few months' time. It will remain closed as construction progresses so that the work in the other construction phases can proceed smoothly. As is sometimes the case with construction projects of this size and scope, work has to be spontaneously reorganised. This is also the case in Schillerstraße, as a utility company will be going into the ground next Monday, 8 July, to carry out pipework. During this work, which is scheduled to last until 19 July, other work in this area will have to be suspended. To ensure that work continues quickly, the sewer house connection work in the 3rd construction phase, from Hainhäuser Straße to Kolpingstraße, will be brought forward. Residents will be informed accordingly. The pharmacy and doctor will remain within walking distance throughout the next construction phase. Parking is available at the community centre or, for a really quick visit to the pharmacy, at the front of Schillerstraße, entrance to Hauptstraße.